How to Read a P&ID: Symbols, Instrument Tags & Signal Lines
In Part 1, we learned what a Piping and Instrumentation Diagram (P&ID) is, why it is important, and how a P&ID differs from a Process Flow Diagram (PFD).
Now let's move to one of the most important skills for an instrumentation engineer: understanding the symbols, instrument tags, valves, piping and signal lines used on a P&ID.
Once you understand these symbols, a complicated P&ID becomes much easier to read.
Note: P&ID symbols and line conventions can vary between companies and projects. The examples below are simplified educational representations. Always refer to the approved project legend and applicable engineering standards when working on an actual project.
1. Equipment Symbols on a P&ID
Process equipment represents the major physical equipment used in an industrial plant. Equipment is normally identified by an equipment tag.
Common equipment includes:
- Pumps
- Storage tanks
- Pressure vessels
- Heat exchangers
- Compressors
- Reactors
- Filters
Pump
Pump — Typical Tag: P-101
A pump transfers liquid from one location to another by adding energy to the fluid.
On a P&ID, a pump may be shown together with suction and discharge piping, isolation valves, check valves, instruments and other associated equipment.
Tank / Vessel
Vessel — Typical Tag: V-101
Vessels and tanks can be used for storage, separation, mixing, reaction or other process functions.
Heat Exchanger
Heat Exchanger — Typical Tag: E-101 / HX-101
A heat exchanger transfers heat between two fluids. The exact symbol depends on the type of exchanger and project drafting standard.
2. Piping Symbols
Piping connects process equipment and allows liquids, gases, steam and other fluids to move through the plant.
When reading a pipe on a P&ID, look for:
- Line number
- Pipe size
- Service
- Flow direction
- Pipe specification
- Valves
- Drains
- Vents
- Instrument connections
Basic Process Line
Process line with flow direction
The arrow indicates the direction of process flow in this simplified example.
Line Number
A process pipeline normally receives a unique line number.
For example:
6"-P-101-150-CS
The meaning of each part depends on the project line-numbering philosophy. It may contain information such as pipe size, service, sequence number, pressure class or material specification.
Never assume the format is universal. Always check the project's line list and P&ID legend.
3. Valve Symbols
Valves are used to isolate, regulate, divert or control process flow.
Some of the most common valves encountered on P&IDs are:
- Gate Valve
- Globe Valve
- Ball Valve
- Butterfly Valve
- Check Valve
- Control Valve
- On-Off Valve
- Pressure Relief Valve
Gate Valve
Gate Valve
Gate valves are commonly used for isolation and are generally not selected for continuous throttling service.
Globe Valve
Globe Valve
Globe valves are often used where flow regulation or throttling is required, depending on the service.
Ball Valve
Ball Valve
Ball valves are widely used for quick isolation and shut-off applications.
Butterfly Valve
Butterfly Valve
Butterfly valves are commonly used on larger-diameter pipelines because of their compact construction.
Check Valve
Check Valve
A check valve is designed to permit flow primarily in one direction and help prevent reverse flow.
4. Control Valve Symbol
A control valve is a final control element. It receives a command from the control system and changes the process flow to maintain the desired operating condition.
Control Valve — Example Tag: FCV-101
A typical flow control loop can be represented as:
FT → FIC → FCV
- FT = Flow Transmitter
- FIC = Flow Indicating Controller
- FCV = Flow Control Valve
5. Instrument Symbols
Instrumentation symbols identify devices that measure, indicate, transmit, or control process variables.
The most common process variables are:
- Pressure
- Flow
- Level
- Temperature
Pressure Transmitter — PT
PT — Pressure Transmitter
Flow Transmitter — FT
FT — Flow Transmitter
Level Transmitter — LT
LT — Level Transmitter
Temperature Transmitter — TT
TT — Temperature Transmitter
Important: The exact shape of an instrument bubble and the line connecting it to the process or control system can depend on the applicable instrumentation standard and project drafting convention.
6. Common Instrument Tags
| Tag | Typical Meaning | Variable |
|---|---|---|
| PT | Pressure Transmitter | Pressure |
| PI | Pressure Indicator | Pressure |
| FT | Flow Transmitter | Flow |
| FI | Flow Indicator | Flow |
| LT | Level Transmitter | Level |
| LI | Level Indicator | Level |
| TT | Temperature Transmitter | Temperature |
| TI | Temperature Indicator | Temperature |
7. How to Read an Instrument Tag
Instrument tags are extremely important when reading a P&ID.
Consider the example:
FT-101
In a typical ISA-style identification:
- F identifies Flow as the measured variable.
- T identifies Transmitter as the function.
- 101 is the identification or loop number assigned by the project.
Therefore, FT-101 generally means Flow Transmitter, identification 101.
For another example:
PT-201
P = Pressure and T = Transmitter.
So PT-201 generally identifies a Pressure Transmitter.
Always verify the exact tag interpretation using the project's instrument index and tagging philosophy.
8. Controller Tags
Controllers perform control functions based on the measured process variable and the desired set point.
| Tag | Typical Meaning |
|---|---|
| PIC | Pressure Indicating Controller |
| FIC | Flow Indicating Controller |
| LIC | Level Indicating Controller |
| TIC | Temperature Indicating Controller |
For example:
LIC-101 generally represents a Level Indicating Controller.
9. Understanding a Complete Control Loop
Now let's connect the individual symbols together.
Suppose we have a tank where the liquid level must be maintained at a particular set point.
The basic control sequence is:
LT → LIC → Control Valve
Step 1 — Measurement
The LT measures the liquid level inside the tank.
Step 2 — Signal
The measured value is transmitted to the control system.
Step 3 — Controller
The LIC compares the measured level with the desired set point.
Step 4 — Control Action
The controller calculates the required corrective action.
Step 5 — Final Control Element
The control valve changes position to regulate the process flow.
This creates a closed-loop control system.
10. Signal Lines on a P&ID
Signal lines show the connection between field instruments, controllers and other control-system elements.
Common signal types include:
- Electrical
- Pneumatic
- Hydraulic
- Digital communication
- Capillary connections where applicable
4–20 mA Signal
A very common analog instrumentation signal is 4–20 mA.
For example:
FT → DCS
The flow transmitter may represent its measured range using a 4–20 mA signal that is received by an analog input channel in the control system.
For example, a transmitter configured for:
0–100 m³/h
could be scaled by the control system so that the 4–20 mA signal corresponds to the configured flow range.
The exact scaling and signal architecture depend on the transmitter, I/O system and project design.
11. P&ID Symbol Cheat Sheet
| Symbol / Tag | Typical Function |
|---|---|
| P | Pump |
| V | Vessel |
| E | Heat Exchanger |
| PT | Pressure Transmitter |
| FT | Flow Transmitter |
| LT | Level Transmitter |
| TT | Temperature Transmitter |
| PIC | Pressure Indicating Controller |
| FIC | Flow Indicating Controller |
| LIC | Level Indicating Controller |
| TIC | Temperature Indicating Controller |
| FCV | Flow Control Valve |
12. How an EPC Instrumentation Engineer Should Read a P&ID
An EPC design engineer should not read a P&ID only to identify instruments.
You should read it from a design perspective.
For every instrument, ask:
- What process variable is being measured?
- Where is the measurement taken?
- What instrument technology is required?
- What is the process connection?
- Is an impulse line required?
- Is a root valve required?
- Is a manifold required?
- Where does the signal terminate?
- Is the signal analog or digital?
- Is the instrument connected to PLC, DCS or SIS?
- Is an alarm required?
- Is an interlock involved?
- Is the instrument part of a safety function?
This is the difference between simply recognizing a P&ID and actually using one for instrumentation design.
13. Documents Used Alongside a P&ID
During an EPC project, the P&ID is normally used together with several other engineering documents.
- Instrument Index
- Instrument Datasheets
- Instrument Hook-up Drawings
- Loop Diagrams
- Cable Schedule
- Junction Box Schedule
- I/O List
- Control Valve Datasheets
- Cause & Effect Matrix
- Instrument Location Plan
Understanding how these documents relate to the P&ID is an important skill for an instrumentation design engineer.
14. Common Beginner Mistakes
1. Memorizing Symbols Without Understanding the Process
Knowing that PT means Pressure Transmitter is not enough. Understand why the transmitter is installed and what happens with its measurement.
2. Ignoring the P&ID Legend
Different projects can use different graphical conventions. Always check the approved project legend.
3. Ignoring Signal Direction
Trace the signal from the field instrument toward the controller and then to the final control element.
4. Treating a P&ID as a Physical Layout
A P&ID represents process functionality and connections. It is not normally an exact physical installation drawing.
5. Assuming Every Tagging System Is Identical
ISA-based identification provides a framework, but individual projects can have additional conventions. Always verify the project instrument index and tagging philosophy.
15. Quick Method to Read Any P&ID
- Identify the major process equipment.
- Find the main process flow direction.
- Follow the main piping.
- Identify isolation and control valves.
- Find pressure, flow, level and temperature instruments.
- Decode the instrument tags.
- Trace the signal lines.
- Identify controllers and final control elements.
- Check alarms and interlocks.
- Refer to the P&ID legend whenever a symbol is unfamiliar.
16. P&ID Interview Questions
What is a P&ID?
A P&ID is a detailed engineering drawing that represents process equipment, piping, valves, instrumentation and control-related connections.
What does PT mean?
PT generally means Pressure Transmitter.
What does FT mean?
FT generally means Flow Transmitter.
What does LT mean?
LT generally means Level Transmitter.
What does FIC mean?
FIC generally means Flow Indicating Controller.
What is a control valve?
A control valve is a final control element used to regulate process flow or another process variable based on a control signal.
Why should you check the P&ID legend?
Because graphical symbols and line conventions can vary between projects. The approved legend defines the conventions used on that particular project.
Key Takeaways
- Learn the meaning behind P&ID symbols rather than simply memorizing them.
- Follow the process flow from equipment to equipment.
- Learn how to decode instrument tags.
- Trace the complete control loop from measurement to controller to final control element.
- Understand the difference between field instruments and control-system functions.
- Always check the approved project P&ID legend.
- For EPC design work, connect P&ID information with datasheets, loop diagrams, hook-ups, cable schedules, I/O lists and cause & effect documents.
Continue to Part 3
In Part 3, we will go beyond individual symbols and learn how to read a complete P&ID from beginning to end.
We will cover:
- How to trace the process through a P&ID
- How to identify complete control loops
- How to read alarms
- How to identify interlocks
- How to understand control valve information
- How to identify instrument connections
- How P&ID information is converted into EPC design documents
- A practical P&ID example
Remember: Don't just memorize the symbols. Understand the process, trace the signal, and ask why every instrument and valve is present.